Daily Operations Update: 22 October 2025
--------------------
Engineering Division
- Construction supervisor, Village No. 1 Road Project, Ban Bo Din Khao – Responsible for grading and leveling the existing road surface.
- Construction supervisor, concrete road project, Village No. 8, Kawkaw, Alley of Mr. Anek, concrete pavement pouring.
- Construction supervisor, Village No. 5 dirt road project, Nong No village. Responsible for laying laterite gravel.
- Construction supervisor, project for the renovation of the early childhood development center, including both external and internal ceiling work.
Electrical Services Unit
- Conduct repairs on the lighting fixtures at Village No. 1, Ban Bo Din Khao.
- Excavated a pit to install additional power poles in Village No. 6, Nong Harn Rangka.
Water Supply Services
- Repairing a 4-inch PVC pipe at Village No. 6, Soi Ban Opat, Teung.
Disaster Prevention and Mitigation Unit
- Conduct cleaning of the temple and the temple hall in Village No. 7, Ban Pho Khoi.
Phrom Nimit SAO Early Childhood Development Center
- Activities included flag raising ceremonies, morning prayers, physical exercise, and the development of teaching and learning methods, as well as comprehensive child development programs.
Caregiver
- Provide care for elderly individuals who require assistance with basic health needs and rehabilitation of physical and functional abilities.
---------------------
Contact Information for the Phrom Nimit Subdistrict Administrative Organization
Call 056-373-903, 056-373-897 (Treasury Department), 056-373-910 (Security Department)
Website: www.promnimit.go.th
LINE ID: @640twaql, or click on this link: https://lin.ee/nc6tBds
Submit the application online: https://www.promnimit.go.th/all_form.php
Facebook: Phrom Nimit Subdistrict Administrative Organization
Tiktok : https://www.tiktok.com/@promnimit_99
กำลังโหลด PDF...